Project Schedule Performance Index (SPI)
Measures project schedule efficiency against planned timeline.
Owner: Unassigned
Updated: 10/30/2025
Calculation Formula
ENGLISH
Earned Value / Planned ValuePython Example
If earned value is $950K and planned value is $1M, SPI is 0.95 (5% behind).Entity Applicability
Which business entities use this KPI
Standard Calculation
8 of 8 entities
100%
Entity-Specific Notes
SPI > 1.0 indicates ahead of schedule, < 1.0 indicates delays.
Entity List (8)
MENA-01•Dubai Terminal
EU-02•Hamburg Terminal
HQ•Headquarters
ASIA-02•Hong Kong Terminal
EU-01•Rotterdam Terminal
ASIA-01•Singapore Hub
US-01•US East Terminal
US-02•US West Terminal
Additional Information
Industry
Construction, EngineeringTags
ConstructionEngineering
Status
activeLocal Network
Data Quality Dependencies
Critical DQ dimensions for this KPI
Accuracy
highThe degree of closeness of data values to real values.
Critical for Project Schedule Performance Index (SPI) accuracy and reliability
Completeness (Data values)
highThe degree to which all required data values are present.
Critical for Project Schedule Performance Index (SPI) accuracy and reliability
Timeliness
highThe degree to which the period between the time of creation of the real value and the time that the dataset is available is appropriate.
Critical for Project Schedule Performance Index (SPI) accuracy and reliability
Quick Stats
DQ Dependencies3
Applicable Entities8/8
Versionv1
API Access
GET /api/kpis/project-schedule-performance-index-spi